The 34-turbine proposal which we call CEP (240 MW), launched on 3 February 2026, should not be the proposal for the Direct Consent Order (DCO) application. It is a quick fix to try to get through the next stages of the planning process. The reason the developers have had to do so much work in a short time is that the Scoping Report was a disaster and has caused a five-month delay already.
The Scoping Report should be abandoned and the consultation process begun again with a correctly designed wind farm.
CWF Ltd have not yet published a proper map of the proposal, and they have not given exact positions for the turbines. All maps are © WTRG.